8th March 2010
- First group meeting - review project briefing
- Discussion of roles
11th to 18th March 2010
- Allocation of roles
- Start of individual research on cranes
- Sketch individual crane idea(s)
18th March 2010
- Discussion and review of individual research on crane concept ideas
22nd March 2010
- Group selection of crane concept
25th March 2010
- Final group meeting before Easter holidays - discuss tasks to be done over the Easter break
25th March to 19th April 2010
- Start of in depth analysis of selected crane concept
- Compilation of full Financial Report - breaking down the cost of crane kit
- Web conferencing (Online group meetings)
19th to 22nd April 2010
- Review of work and addition of final touches
23rd April 2010
- Closure of Tender proposal - submission of work
23rd to 25th April 2010
- Compilation of Tender Presentation
26th April 2010
- Submission of Tender Presentation
26th to 27th April 2010
- Preparation for Tender Presentation
28th April 2010
- Group delivery of Tendering Presentations (10mins Long)